DCS投入与厂用电受电工期配合
厂用电源控制纳入DCS后,由于不设独立于DCS的硬手操,而根据以往电厂施工经验,在倒送厂用电时,DCS一般尚未投运,此时高压启/备变、高/低压厂用电源操作无法实现,故要求DCS设备安装、调试及投运在工期上予以配合。在厂用电设备安装调试的同时,开展了DCS的安装调试,特别是与厂用电有关的子系统的调试,使其投运在倒送厂用电之前,以满足电气倒送厂用电、厂内各工艺系统的分部试运行的要求。